|
 |
2000 |
Major work was needed on the north approach to the
bridge, as well as the various abutments over the Ti. |
Shawn Noe |
|
 |
2000 |
The bridge sat for forlorn for about thirty years covered
in vines. The track was re-laid for about a mile after the bridge.
It once led about to the towns of McGraw, Solon, and Cincinnatus. |
Shawn Noe |
|

|
April 12, 2001 |
4008 and 3040 switch SuiteKote. |
Joshua K. Blay |
|
 |
April 12, 2001 |
4008 and 3040 shove from SuitKote towards the Syracuse branch. |
Joshua K. Blay |
|
 |
May 28, 2001 |
2012, often called "the
workhorse of the northern division," has the day off on Memorial Day right near the team track facility, just off the
Syracuse main. |
Joshua K. Blay |
|
 |
Summer 2001/2002 |
Two SD45s, a GP20 and a B40-8 switching cars.
DL&W/EL only sent 44 tonners and SW-1s on this branch due to light bridges
beyond McGraw. |
Eric Robb |
|
 |
July 6, 2003 |
Overall view of the 4 tracks SuitKote, a forth added
earlier in the year. Taken with permission. |
Joshua K. Blay |
|
 |
August 27, 2003 |
3040 shoves empty tank cars towards the main, east
of Franklin Ave. |
Joshua K. Blay |
|
 |
September 8, 2003 |
The other customer besides the asphalt plant is a team
track to serve Bestway Lumber. Bestway is a busy year-round customer. 116 on the team track. |
Joshua K. Blay |
|
 |
February 9, 2004 |
Nearly the same spot, 5 months
later. |
Joshua K. Blay |
|
 |
May 5, 2004 |
Empty centerbeam flatcars being switched off the team
track by 116. |
Joshua K. Blay |
|
 |
May 5, 2004 |
SY1 after switching the team track. |
Joshua K. Blay |
 |
May 7, 2004 |
2064 on the team track with more lumber for Bestway. |
Joshua K. Blay |
smallname_small.JPG) |
July 2, 2007 |
New track in Cortland Junction! One of the few
rumors that becomes truth- a wye is being built to allow for better access
to the Cincinnatus Branch. Here's the new switch to be installed on
the mainline, a little ways south of Port Watson Street. This is all
NEW track, there never was a wye here in the "good ole days." |
Joshua K. Blay |
smallname_small.JPG) |
July 2, 2007 |
Another view. |
Joshua K. Blay |
smallname_small.JPG) |
July 2, 2007 |
The north leg of the wye will curve to the left.
The right of way is mostly graded. The west leg is the main, the south
leg is the original right of way installed after the DL&W took over the
Cincinnatus branch. |
Joshua K. Blay |
smallname_small.JPG) |
July 2, 2007 |
The day I discovered the new work, the second of two new
switches had already been constructed, and personnel had just removed the
bolts, joint bars, and spikes freeing rails to be pulled for the
installation of the new switch. |
Joshua K. Blay |
smallname_small.JPG) |
July 2, 2007 |
A second view of the rails being pulled. The new
switch is the other side of the branch. |
Joshua K. Blay |
smallname_small.JPG) |
July 4, 2007 |
Two days later the switch is installed, and SuitKote is
again connected with the nation's rail network. Track to the left is
the original DL&W right of way. |
Joshua K. Blay |
smallname_small.JPG) |
July 4, 2007 |
Again, curving to the left is the DL&W right of way.
The Cincy's original construction and operation was originally contracted
out the Lehigh Valley. The new wye partially follows the connection
the Lehigh. After the DL&W took over the Cincy, they installed the
connecting track to the DL&W Syracuse branch south of the LV/DL&W diamond.
The new track will cross where the gondola is in the distance- the team
track is to be relocated. The yellow dump truck at the
right background is almost on the Lehigh right of way, which once led to
Cazenovia. |
Joshua K. Blay |
smallname_small.JPG) |
July 4, 2007 |
A second track will soon cross South Franklin Street,
look closely and you can see survey markings for the center line of the new
track. |
Joshua K. Blay |
 |
August 31, 2007 |
Almost two months later and much
progress has been made. The second switch has been installed in
addition to a lot of new
track has been laid down. No ballast and the two sections are not
connected yet. |
Joshua K. Blay |
cropname_small.JPG) |
October 29. 2007 |
The track has been completed, ballasted, and appears to
be in service. |
Joshua K. Blay |
|
|
|
|
|